Caroline County Health Department
Division of Environmental Health
403 S 7th Street, P.O. Box 10, Denton, MD 21629
Hours 8-5p.m., M-F; Phone: 410/479-8045    FAX: 410/479-4187


[E/H HOME PAGE]   [FEE SCHEDULE]    [FORMS/APPLICATIONS]    [QUESTIONS-ANSWERS] Caroline County Health Department, Maryland

PERC QUESTIONS


Checklist for perc test (and subdividing):

  1. Check with Planning & Codes at 410 479 8100 to make sure project can be done.
  2. Prepare site
  3. Prepare scaled site plan showing location of test site. Include location of any wells within 150 feet of the existing and proposed property lines. Note on your site plan if no wells within 150 feet of property lines.
  4. Apply for Perc Test: Submit application (signed by legal owner) site plan and appropriate fee. Expect results of soil evaluation (dry perc) within 60 days of application; if wet season test, expect results at end of wet season (usually in June, provided wet season application was received by December 1st and no drought conditions exist).
  5. Apply for Plat Evaluation -- Submit plat (if subdividing); or
  6. Apply for Septic permit (if no subdivision required and are ready to build).


What are perc tests?   Perc tests are soil and site evaluations performed on a parcel in a location where one would install a septic system. Certain criteria must be met, such as having a valid perc approval before a septic permit will be processed.

Before a test can be performed, certain issues must be addressed. The applicant should ask themselves the following questions BEFORE applying for a perc test:



Who does perc tests?    Perc tests are evaluated by a registered sanitarian in the health department, upon receipt of application, current fee, and acceptable site plan.

In cases where the parcel in question is very large and you are not sure where you want to have the perc test performed, recommend contacting a soil consultant to suggest test sites.

It is the applicant's responsibility to prepare the site. Most of the sewage contractors in Caroline County prepare perc test sites.



When can perc test be done?     Before that can be answered, consider the fact that perc tests are broken down into three categories: Soil Test, Wet Season Test, Sand Mound Test and are described below:


Where can perc test be done?    The health department does not determine where a perc test can be performed. However, it is recommended that the test site be approximately:

Clear an access to the test site.   Please keep access clear until written results have been received.


How much will perc test cost?    The testing fees will vary depending on what type of perc test being applied for. The fees are also determined by the number of sites being tested. Examples follow.

The point is, one perc test site may require up to three different fees--the soil test fee, the wet season test fee, and the sand mound test fee; OR one perc test site may only require the single fee of the soil test. The initial soil test (pits) will determine if wet season testing is required. The wet season test will determine if a regular septic system can go on site, or if a mound test option is available.

Remember, however, that the majority of the soils in this county are wet season soils, so it is highly probable that Example C will be the cost.

Refer to the fee schedule to get the current fee

Note that the testing fee does NOT include preparing the site.    Most sewage contractors could prepare the site, the cost may vary. Call a contractor for prices.



How long are perc approvals valid and can they be extended?    Perc approvals are valid for two years; however, if the site is not maintained the perc approval could be rescinded. In other words, make sure no one puts a pond, ditch or well in or too close to the test site. Also make sure the site is easily found on the property, especially if the home is not going on the parcel for a few more years.

Apply for a Property Status Report, to see if your perc approval can be extended, allow 30 days processing time.

In cases where you plan to subdivide the perc approved property off of a larger parcel; the perc is considered temporary and is valid for six months --until a plat is recorded. Then the perc is valid two years from the date the health department signed the plat.


Perc disapprovals, what are my options?    When a perc disapproval letter is issued, options are noted on the letter.   Sometimes a mound test option is available; other times the only option would be to get public water/sewer if it comes to the area.   Do not assume that a mound could go on any property that does not pass a perc test.

Not all perc disapprovals will give a mound test option; nor do all mound test options pass.


Site Preparation:

Below is a cross section of a test pit and piezometer (pipe). Note the pit should be no deeper than 5 feet and at least 3 feet wide--a gentle slope would be needed to allow someone access into the pit. The pipe should be approximatley 10' from the pit.

Recommend you read SITE PREPARATION FOR PERC TESTS for more details in preparing your test site.


Site Plan:

The site plan should show the following:

Below is an example of a perc test site plan for a vacant lot (no existing buildings, driveways, wells on test parcel). Notice it shows entrance to property as well as the location of pits, pipes and property lines. It also shows the closest well to test site is on adjacent parcel.

site plan of pits and pipes

Please note, in cases where the property is very large, include copy from Tax Book--your initial site plan can show pit/pipe locations with notation of distance from two of the closest property lines.    Remember, pits to be 100 ft apart and 150 ft from any wells, rivers, streams, ponds, ditches, farm field drainage systems. The pipes are to be approximately 10 ft from the pits. Refer to "SITE PREPARATION FOR PERC TESTS"


copyright  ©  CCHD2006 ¦ Legal Disclaimer & Privacy Notices;   Leland Spencer, M.D., Health Officer
Comments to: belindar@dhmh.state.md.us